2026-03
Week 1 (March 2-7): v0 Wrap-up
Section titled “Week 1 (March 2-7): v0 Wrap-up”Wrap-up v0: Should be end-to-end usable
- Frontend implementation of contractor org dashboard, admin / member inboxes
- User Authentication finalized & implemented
- Email notifications for v0 are live
- Final Bond Form Implemented (Including frontend implementation of final bond pre-request survey)
- Implementation of Huddle internal dashboard
Week 2 (March 9-13): QA Week 1
Section titled “Week 2 (March 9-13): QA Week 1”- Debugging
- Front-end language adjustments
- RAG Accuracy benchmarking, retrieval/indexing strategies, prompt engineering
- Implementing observability tools
- Internal end-to-end testing with dummy accounts
- Determining unit costs
- Note: This item is important as its currently a blocker for our pricing strategy, financial planning, and angel fundraising efforts
Week 3 (March 16-20): QA Week 2
Section titled “Week 3 (March 16-20): QA Week 2”- Low-risk optimization across the full stack of our application based on week 1 QA assessment
- Continued internal end-to-end testing
- Reducing product risk for live demos
- Q/A wrap-up
Week 4 (March 23-27)
Section titled “Week 4 (March 23-27)”- Set up agency accounts with dummy contractor organizations for live demos
- Prepare in-person presentations and tailored questions for meetings with agency staff-team
- Pray that our app works lol